IBJNews

Nucor Steel struggling to strike new power deal with Duke Energy

Back to TopCommentsE-mailPrint

In a year’s time, Nucor Steel devours as much power as 200,000 homes. Its annual electric bill runs in the tens of millions of dollars for the 1 billion kilowatt hours it takes to melt rusty scrap into new metal.

So determining what the Crawfordsville mini-mill will pay for that power is no small matter. And it has struggled over the last two years to forge a new long-term power-supply deal with Duke Energy.

Nucor last month complained to the Indiana Utility Regulatory Commission, asking it to establish a rate schedule containing “reasonable and just charges.”

Nucor’s existing deal, which was set to expire at the end of next month, has been extended, but only through February.

After two years of negotiations, “we are far apart” with Duke, said Pete Mattheis, an attorney for Nucor at the Washington, D.C-based law firm Brickfield Burchette Ritts & Stone.

Nucor, which employs 731 in Crawfordsville, including a number of workers from the Indianapolis area, won’t say what happens if it can’t secure a new long-term agreement within its parameters.

The North Carolina-based steelmaker points out that it has three similar mini mills—in Alabama, Arkansas and South Carolina—that could absorb some of the work. Nucor stated in its most recent financial filings that “almost all of our steel products facilities are operating at less than 50 percent” of capacity.

“Nucor has at this point sister mills that make this product. There are options,” said Mattheis, declining to elaborate.

Mattheis’ local co-counsel is Anne Becker, Indiana’s former consumer utility counselor who now practices at Indianapolis law firm Stewart & Irwin. Becker said Nucor appears to be Duke’s largest Indiana customer. Both Nucor and Duke are based in Charlotte, N.C.

Mattheis said the inability to come to terms on an electricity supply agreement “is something very unusual for Nucor.”

Exactly what the sticking point is in talks is unclear; neither side will elaborate.

Duke is preparing to file a response to Nucor’s complaint with the IURC, said utility spokeswoman Angeline Protogere. Nucor plans to file testimony with the commission by Sept. 18.

Protogere noted that Nucor’s contract was negotiated 20 years ago, when the company opened its Crawfordsville mini-mill. In the first 10 years, Nucor paid a so-called economic development rate that was part of an incentive package the state offered to attract and bolster new business.

“So, for over a decade, Nucor’s rates were among the lowest in our system. Costs have risen significantly over those years” as Duke made capital investments around the state, Protogere said.

“It’s important that all customers pay their fair share. Our industrial rates are very reasonable and among the lowest in the nation,” she added.

Nucor opened a $300 million “mini-mill” in Crawfordsville in 1989.

In the decades prior, mini-mills were relegated largely to using their electric furnaces to melt scrap metal for so-called non-flat products, such as reinforcing rods and rails.

By contrast, traditional “integrated” steel mills, which made steel by cooking iron ore in a blast furnace, commanded the higher-end market for flat steel used in autos and appliances.

Nucor’s Crawfordsville plant would make history. According to a study of Nucor by the Tuck School of Management at Dartmouth University, the Crawfordsville mini-mill was the first to mass produce the more lucrative flat-steel products. Nucor had licensed German technology that had been deployed earlier but only to the extent of a small pilot program.

Today, about 30 mills are patterned after the Crawfordsville facility, said Chris Cox, controller of Nucor’s Crawfordsville division.

Company officials say steel produced at the plant has gone into such projects as Lucas Oil Stadium, The Children’s Museum of Indianapolis, the FedEx hub at Indianapolis International Airport and Community Hospital’s south campus.

In its complaint with the commission, Nucor said electric power costs are one of its principal variable input costs.

“Nucor competes in the highly competitive global steel markets. A competitive electric rate for the Crawfordsville plant is critical for the ongoing competitiveness and success of [the plant] … Given the importance of electricity in the process, the availability of reasonably priced electricity is vital to the plant’s success.”

In a strategy to get power cheaper, Nucor buys power from Duke on what’s known as an interruptible basis. That means, except for a portion of load going to key pieces of equipment, Duke can temporarily shut off power to the Crawfordsville plant during periods of peak power demand.

“Nucor has chosen to take interruptible service, despite the costs and risks of interruptibility, due to the critical need for a competitively priced supply of power,” Nucor said in its complaint with the IURC.

Absent a new supply agreement, the steelmaker would have to pay a firm rate for non-interruptible service. If so, “I would guess that our costs would probably at least double,” Mattheis said.

Nucor argues that continued interruptible electric service won’t hurt other Duke customers and would not require Duke to accelerate its power generation capacity. “This would not be true if Nucor were required to take firm [uninterruptible] service for its total load.”

Becker noted that Duke and other utilities have been trying to get more customers to agree to let the utility switch off service during peak demand as a way to reduce stress on the system and defer the need for costly new generation capacity.

“Nucor is the original demand-response resource customer,” she said.

Given Indiana’s regulatory restrictions, Nucor doesn’t have the ability to purchase power from other providers. Building its own generation capacity is considered an impractical departure from its core steel business.

“We want them to be successful and we will continue to try to work with them to reach an agreement,” said Duke’s Protogere.•

ADVERTISEMENT

Post a comment to this story

COMMENTS POLICY
We reserve the right to remove any post that we feel is obscene, profane, vulgar, racist, sexually explicit, abusive, or hateful.
 
You are legally responsible for what you post and your anonymity is not guaranteed.
 
Posts that insult, defame, threaten, harass or abuse other readers or people mentioned in IBJ editorial content are also subject to removal. Please respect the privacy of individuals and refrain from posting personal information.
 
No solicitations, spamming or advertisements are allowed. Readers may post links to other informational websites that are relevant to the topic at hand, but please do not link to objectionable material.
 
We may remove messages that are unrelated to the topic, encourage illegal activity, use all capital letters or are unreadable.
 

Messages that are flagged by readers as objectionable will be reviewed and may or may not be removed. Please do not flag a post simply because you disagree with it.

Sponsored by
ADVERTISEMENT

facebook - twitter on Facebook & Twitter

Follow on TwitterFollow IBJ on Facebook:
Follow on TwitterFollow IBJ's Tweets on these topics:
 
Subscribe to IBJ
  1. In my opinion the estridge companies are crooks. They filed bankruptcy on their 'track housing' side of the business two weeks before they closed on one of my clients' homes. When my client first interviewed Estridge as a builder 6 months before, they specifically ASKED about the solvency of their business, knowing that some builders were struggling. Estridge truly misrepresented their financial situation at that time. I suppose I am more unhappy with the whole system than I am with the builder because what the heck==you can file bankruptcy on 'track homes' but still keep building and make money off of 'custom built' homes??? How ridiculous! They are all homes. How can a company be allowed to bilk thousands of dollars from their subcontractors but still be allowed to build houses?? they should have been made to pay back all their unpaid contractors before being allowed to profit from building any more houses! This alone makes them and the system crooks in my eyes. I would never build an estridge home and I would not recommend for my clients either. If they were truly 'bankrupt' how could they afford to keep building homes anyway??? The whole system needs fixed.

  2. I live a couple blocks east of the Angie's campus and my house is assessed for ~$160,000. If I could get that amount, let alone $384,000 (a 140% bonus), I'd sell in a minute. Either Angie's stockholders just got fleeced, or Angie's is getting about a 58% discount on their property taxes, if these properties are actually worth what they paid Mr. Oesterle for them. Which do you think is the case?

  3. Perhaps the IMA board is really to blame! They agreed to hire Charles. They can't seemingly find donors among themselves, or bring in new blood that will support the museums operating budget with an expanded museum and money to provide curators with something to do (ie buy art). The headlines of disarray at the museum and mass firings are hurting the reputation of the museum for some time to come. If people on the board had misgivings, perhaps they shpuld have more forcefully opposed efforts that they have seemingly been unable to fund, like expansion and the costs it has created!

  4. See, I told u Indyman and Dipsicle....this 8 days is overkill. It's barely worth a weekend....great job Tony George! Your dream has been fulfilled....he fans want the I r l back. Thats how good it was.....and that sucked.

  5. I have been in training for a short time now but right off I can see that safety and quality are the number one issues, my experience as of late has been a positive one, the employees along with Jeff the plant manager and the operation supervisor as well as the engineers are a highly motivated group of people, what an asset for the area to have and for company's in need of a quality metal products.

ADVERTISEMENT