City bailout keeps plan alive for Gold Building

  • Comments
  • Print
  • Add Us on Google
Listen to this story

Subscriber Benefit

As a subscriber you can listen to articles at work, in the car, or while you work out. Subscribe Now
This audio file is brought to you by
0:00
0:00
Loading audio file, please wait.
  • 0.25
  • 0.50
  • 0.75
  • 1.00
  • 1.25
  • 1.50
  • 1.75
  • 2.00

The $18 million mortgage from Cincinnati-based First Financial Bank allowed Gershman and Citimark in 2019 to purchase the Gold Building and the two buildings directly east of it. (IBJ photo/Chad Williams)

A city commission is backing the Hogsett administration’s effort to salvage the long-planned redevelopment of the Gold Building downtown, which for months has been hampered by financial challenges that nearly derailed it.

The city is giving local developers Gershman Partners and Citimark an $18 million bridge loan to avoid foreclosure—something sources told IBJ was a near certainty if the firms didn’t soon pay off the debt incurred when they bought the 20-story office tower and two adjacent buildings in 2019.

While the developers proposed the redevelopment in 2022, they’ve failed to finalize their funding on the project due to several persistent problems. That forced the city to step in with its loan, which was unanimously approved by the Metropolitan Development Commission on Wednesday afternoon.

Originally the result of a public-private partnership between Gershman and Citimark and the Department of Metropolitan Development, the project included overhauls of the Gold Building and two other properties on the northern half of the block bordered by Ohio, Alabama, Market and Delaware streets, as well as the City Market property and its east plaza. (A $15 million redevelopment of the west plaza was added to the mix in January.)

The Gold Building conversion at 151 N. Delaware St. is expected to replace 400,000 square feet of vacant office space with more than 350 apartments and nearly 8,000 square feet of ground-floor retail, as well as a cleaned-up Wabash Street alley between the northern and southern halves of the block.

Over the past two years, Gershman and Citimark have invested about $15 million on renovations for the 251 E. Ohio St. office building on the southwest corner of Ohio and Alabama streets and the parking garage between that structure and the Gold Building.

Sources close to the deal have told IBJ the project has been a point of frustration for months for Indianapolis Mayor Joe Hogsett, his administration and other economic development insiders at the local and state level. That’s both because of the faltered efforts to secure funding and because the setbacks have led to delays for other components of the effort to reshape City Market.

Three sources familiar with the Gold Building deal told IBJ the redevelopment nearly fell through this spring, before the city and Indianapolis Economic Development Inc. stepped in to negotiate the bridge loan to stave off foreclosure.

Each source spoke on the condition of anonymity because they were not authorized to speak publicly on the matter.

The MDC’s vote means city officials and the developers can finalize their loan agreement, lining up the developers to complete their project financing by the end of the year, which they told the commission is their intention.

Carmel-based Merchants Bank will provide the construction loan while local developer Milhaus has signed on as an equity and development partner.

Redevelopment plans for City Market and its east plaza have been delayed by the Gold Building redevelopment setbacks. (IBJ photo/Chad Williams)

Foreclosure threat

The insiders each separately told IBJ the developers had exhausted their options on the original $18 million mortgage for the Gold Building and the two other buildings on the northern half of the City Market block.

The sources said the firms were at risk of a foreclosure suit from Cincinnati-based lender First Financial Bank until the city stepped in—a threat that could have been back on the table without final approval on the city’s loan offer.

According to public records, the $18 million mortgage first came due in March 2022, but the sources said the term was extended multiple times over the past three years to allow Gershman and Citimark time to redevelop the properties.

The bank gave the developers yet another extension on their mortgage only because the Hogsett administration became more directly involved in the project, each of the sources said.

Eric Gershman

But Eric Gershman, partner at Gershman Partners, disputed the sources’ characterization of foreclosure concerns in an interview with IBJ.

He said while the development team has received multiple 12-month extensions on the loan and that First Financial wanted out, there have “never been any threats” from the bank requiring the loan be paid off by a certain date, nor has the developer ever been reprimanded for its delays on the project.

“We have definitely never missed a payment and are not in default of the loan,” he said. “The loan has been extended, and [First Financial] would like to be paid off, as they’ve been patient with us—they want to move on. So we’re working to pay them off when we do the development.”

Office owners typically refinance or sell at the end of a loan term, but with redevelopment plans in play, the firms held on. Banks are reluctant to foreclose on properties, especially ones involved in a potential redevelopment project, because doing so can limit the amount they could recover.

Foreclosures are also a last resort for developers because they can create costly legal problems and damage the developer’s reputation with lenders and the public.

Gershman said the First Financial mortgage was tied to a planned office building refresh, not a full redevelopment.

The city is expected to pay the developers a lump sum that would be passed on to First Financial to satisfy the original mortgage balance. The city would then assume the debt on the project—giving it legal authority to take the properties if the redevelopment funding plan fell through.

The city’s deal with Gershman and Citimark gives the developers more time to close on a construction loan to finance the rest of the project.

The Indiana Economic Development Corp. has also agreed to provide $10 million in redevelopment tax credits for the project, an offer made by then-Gov. Eric Holcomb’s team. When Gov. Mike Braun took office in January, his office reviewed the incentive, which delayed a final commitment.

“The state has been at the table with us the whole time through the change in administration,” Gershman said. “They wanted to review where their priorities were, and there was a delay, but no fault of their own. … They stayed with the project, and we’re working with them to finalize the state incentives.”

Additionally, the state has offered up to $10 million more through the Regional Economic Acceleration and Development Initiative, according to the agreement for the bridge loan.

In addition to written commitments from the developers’ lenders and partners in the project, the city has asked for letters of commitment from the state for its redevelopment tax credits and READI funds allocations before it’s willing to finalize the loan for the developers. A spokesperson for the IEDC did not respond to a request for comment or an interview.

Gershman said the deal was sidelined from its original late 2022 start by continued conversations with the city and state related to incentives, as well as continued uncertainty related to the development market. He said those concerns have been further compounded by changes at the federal level, including tariff worries.

Inside the deal

The city’s $18 million loan would not replace the up to $18.8 million in tax-increment-financing bond incentives approved in early 2023 for the entirety of the City Market block redevelopment. Instead, it takes the place of a separate $13 million loan that was approved in 2024 but never materialized.

The new loan would be funded through money from the city’s consolidated downtown TIF district—a separate funding mechanism from the already-approved bonds.

The loan also would be eligible for forgiveness if certain conditions are met, either outright or through a schedule in which the city would essentially reinvest funds in the project. A copy of the loan forgiveness schedule was not immediately available.

According to the agreement, the city would be able to withdraw its loan offer if Gershman and Citimark don’t secure construction funding. The agreement also requires the developers to meet monthly with their financial partners, the DMD and Indianapolis Economic Development Inc.

The companies must finalize their construction loan within nine months of securing the bridge loan and repaying their original bank.

If the construction loan or other parts of the developers’ plans fall through and prevented the redevelopment from securing the needed funds, the developers would be required to repay the loan immediately, with 7% interest—and to give up all three buildings on the northern half of the block to the city.

The city initially considered whether it should buy the property directly from the bank and find another partner for redevelopment, sources said. But it ultimately decided retaining the current partnership was wiser.

Megan Vukusich

If the city did gain possession of the Gershman and Citimark buildings, it would likely solicit redevelopment proposals, with two sources telling IBJ the Hogsett administration would be open to demolition of one or more of the structures, including the Gold Building.

The loan agreement includes a shared appreciation clause that allows the city to profit from any sale of the property within a certain period. Those clauses have become more popular with the city of late, particularly on projects that received city assistance but could be sold within a few years of their completion.

Megan Vukusich, director of the Department of Metropolitan Development, told IBJ the loan improves the chances that the project will come to fruition.

Delays and city decisions

Gershman and Citimark have been eyeing updates to the Gold Building since early 2020, although plans evolved from office space renovations to a focus on multifamily and retail in the wake of the pandemic.

In response to the city’s request for proposals for the southern half of the block, including City Market, in early 2022, the developers offered a concept that aimed to blend the market property with their own plans for the area.

Along with the Gold Building redevelopment and $40 million in total investment for its other two properties on the northern half, Gershman Partners and Citimark floated a separate $40 million apartment tower for the City Market east plaza—a project not currently moving forward.

The city announced in June 2022 it had chosen Gershman’s and Citimark’s proposal from three finalists, besting concepts from TWG Development LLC and Flaherty & Collins. At the time, city officials said the companies’ ownership of all three buildings immediately to the north significantly affected planning around City Market.

But the ongoing challenges with the Gold Building led the city this July to withdraw its partnership with Gershman and Citimark on the west plaza project.

The planned $15 million project is expected to expose most of the historic Indianapolis Catacombs as part of an outdoor amenity that will still serve as the new front entrance to the office-to-apartment conversion.

The city last month issued a request for proposals to find a new developer to build that space. Sources said the city didn’t want to risk further delays to those plans because of Gershman’s and Citimark’s challenges.

Eric Gershman said he did not consider the move to be retribution for delays to the Gold Building project but instead “more of a divide-and-conquer” approach that will allow the Gold Building and west plaza to be under construction concurrently. It would also allow the city to begin reevaluating overall plans for City Market—which has been closed since March 2024—as the Gold Building delay has largely stymied conversations on that component.

He said he’s hopeful his company and Citimark might still be a part of City Market’s eventual east plaza redevelopment, but DMD’s Vukusich said discussions on that matter have been tabled until the conversion project is further along.

“We want them focused on the Gold Building,” she said.•

Please enable JavaScript to view this content.

Story Continues Below

1 Comment

Editor's note: You can comment on IBJ stories by signing in to your IBJ account. If you have not registered, please sign up for a free account now. Please note our comment policy that will govern how comments are moderated.

  1. Will the City Hall/21C development be the next to ask for additional City funds again. Hopefully the City has learned a lesson not to use local developers unless they are teamed with a national development company to ensure they can financially make the project work. If the City has approved funding for the Gold Building why can’t construction start later this year.

CYBER DEAL: 50% OFF a subscription to Indiana Business News.50% OFF an annual subscription UNLOCK TODAY

50% OFF

An annual IBJ subscription.

UNLOCK TODAY Offer expires
Monday, November 30.
For new subscribers only.

Already a paid subscriber? LOGIN!

IBJ Media publications wrapped as gifts

50% OFF

An annual IBJ subscription.

UNLOCK TODAY

CYBER DEAL

The inside scoop on Indiana business is waiting.

Offer expires Monday, November 30. For new subscribers only.
IBJ Media publications wrapped as gifts