Completion date for I-69 extension delayed again

Indiana officials have again added time to the projected date to complete construction of the Interstate 69 extension segment between Bloomington and Martinsville.

The Indiana Finance Authority said in a notice to bond holders it estimates work on Section 5 will be substantially completed by Aug. 31, 2018, three months later than previously estimated, The Indianapolis Star reported.

The section has been plagued by delays since work started in 2014. It was originally scheduled for an October 2016 completion.

The IFA said it was negotiating with bond holders "to secure control of the completion of the Project by IFA and resolve outstanding issues."

It said $236.8 million was needed to complete the project, but only $72 million was available. That means $164.8 million is needed to "complete construction and resolve claims."

Please enable JavaScript to view this content.

Story Continues Below

Editor's note: IBJ is now using a new comment system. Your Disqus account will no longer work on the IBJ site. Instead, you can leave a comment on stories by signing in to your IBJ account. If you have not registered, please sign up for a free account now. Past comments are not currently showing up on stories, but they will be added in the coming weeks. Please note our updated comment policy that will govern how comments are moderated.