Subscriber Benefit
As a subscriber you can listen to articles at work, in the car, or while you work out. Subscribe Now
Chad Williams)
Indianapolis-based developer Christopher P. White’s goal was to have an ambitious 46-acre mixed-use project in the Martindale-Brightwood neighborhood largely completed two years ago.
Instead, the group behind Monon 30 has opened just one of several planned residential complexes. And four years after the project was first proposed, the group is still submitting and altering plans for the rest of the project on several former industrial properties along the Monon Trail.
In 2021, White and eight other partners rolled out a vision for the area between 30th and 33rd streets that included dense housing development and sprawling commercial spaces. At about the same time, the group launched “The Cradle at Monon 30,” an event space and beer garden with a dog park that played host to concerts and pop-up events.
In a July 2022 headline, Indianapolis Monthly declared The Cradle “breathes life into urban blight.”
But that outdoor event space has disappeared without much explanation. And only the one Monon 30 building—a 221-unit apartment complex called The Domino—has come to life.
In addition to The Domino apartments, the Monon 30 project was to have included 120 townhouse-style apartments and multiple restaurants and retailers, including a 25,000-square-foot neighborhood grocery store.
White said he and Monon Development Group LLC still have plans to develop at least two more residential projects. And he said several plots of land are slated for multi-use or commercial development and recreational space with pickleball and volleyball courts.
The group of companies that make up Monon Development Group (called the M30 Collective) has grown to 13: Monon 30 Group, Job Capital, Sullivan Development, Glassburn Properties, Crane Construction Group, Midwest GC, The Ridge Group, DMJR Development, Mojave Ghost Blackhawk, Premier Commercial Real Estate Services, Architects Forum, Gradison Design-Build and CCA Sports.
But the group’s plans have been drawn out by complicated administrative issues that have taken about three years to overcome, White told IBJ.
Development delays
White said a legal dispute between the city and his development group over land ownership regarding the Monon Trail right of way took until October 2022—about a year—to resolve.
“We had a meeting, and within 10 minutes we resolved everything, instantly and amicably,” he said. Still, the deed transfer took an additional six months.
Then beginning in 2023, the city and the development group engaged in a yearlong back-and-forth over traffic flow near the project. Ultimately, the Metropolitan Development Commission voted to allow access to city-owned land to build a connector road to Sutherland Avenue. White said the deed for that land again took about six months to secure.
White said he believes current planning administrators have sympathy for the fact that he’s been working on the project for four years and said the parties are past the disputes. Now he’s planning for the entire 46-acre project, including commercial development, to be completed in 2027.
Molly Kruger Sanford, a former communications director for Monon 30 Development, told IBJ it felt like the city approval process presented one hurdle after another.
“They have not made it easy on Chris White to follow through with his vision of doing something really wonderful for this neighborhood that hasn’t been touched in years,” Sanford told IBJ. She helped coordinate events and plan for The Cradle at Monon 30.
“It’s so frustrating, because I have so many friends that are just like, ‘what’s going on with it? What’s going on?’… I don’t know the answer at this point, but I just know things are being held up,” she said.
Sanford works now as an interior designer, creating renderings of home renovations for her own company. That’s because the delays in development meant that she and other Monon Development Group staff ran out of work, she said.

complexes and several commercial buildings as part of Monon 30 in the Martindale-Brightwood neighborhood. (IBJ photo/Chad Williams)
What’s next
The Domino was one of two Monon 30 housing developments approved in September 2022 to receive a combined $15.3 million in TIF-backed bonds from the city.
The apartment complex began leasing at the start of the year. Muncie-based general contractor The Ridge Group built the structure. The housing unit’s name has meaning: The complex is the “first domino to fall” in a planned lineup, White said.
The city’s Metropolitan Development Commission in July OK’d plans for the second apartment complex, the 90-unit The Queue. Workers will begin construction this month, White said.
Twenty-six acres for a third housing development, to be called TurnStyle (previously Monon 35) was approved to be rezoned in May 2024. The property at 3500 Southerland Ave. will eventually be an apartment complex with 500-600 units. White and his partners plan to seek a low-income housing tax credit for about 200 units at TurnStyle. Those federal credits are awarded by the Indiana Housing and Community Development Authority.
“Most of our approval hurdles have now been overcome,” White told IBJ.
Now that the residential aspects of the project are in motion, the group can begin work on developing its commercial plans.
White hopes to submit an updated plan for those parcels to the Department of Metropolitan Development within the next two months so construction can potentially begin next spring, he said.
“The commercial is dependent upon the residences,” White told IBJ. “That’s what makes the commercial successful.”
Tenants that had originally planned to be part of the project’s retail lineup have since gone elsewhere, meaning the Monon Development Group has had to find new tenants for the spaces.
A community project
White is the former leader of Premier Properties USA Inc., which in 2005 opened the 600,200-square-foot Metropolis Mall in Hendricks County, later named The Shops at Perry Crossing.
He was convicted of felony fraud in November 2009 after allegedly writing a bad check to make payroll for his company. He maintains he was wrongly convicted.
The company filed for Chapter 11 bankruptcy in April 2007, and a month later, a judge converted the case to Chapter 7 and ordered the company liquidated.
White says those challenges are in the past.
As the key stakeholder making Monon 30 a reality, he’s made it a point to work closely with the community. He convened a community group that has met regularly over the last three or four years to discuss the project.
“The community and I get along great,” White said. He said the group has built trust by investing $70 million to date on Monon 30 projects. “So I think people that know me are fine with me,” he said.
Johnnie Alex, a retired marketing executive for IBM and longtime resident at Hovey and 30th streets, acknowledged that the projects aren’t coming together as quickly as expected. However, she said White has provided neighborhood leaders a peek behind the curtain that shows just how difficult it is to execute projects of this kind and size.
“I’m still positive that it’s going to work out, because now I know that it takes time. It doesn’t just happen overnight,” Alex told IBJ. “You don’t just go and ask for a permit and get it.”
As for the event space, White says it was never intended to be permanent—as construction would eventually interrupt its operations. It was meant to prove that people were willing to come out to a part of the Monon Trail that had been surrounded by abandoned buildings and neglected.
“We were able to demonstrate that we could attract over 3,000 people in a day to the area, so that the volume of people that you need to support the community, or to support the commercial is available,” White said.•
Please enable JavaScript to view this content.

Over promising and under delivering is the name of the game in Indy.
Taylor,
Seriously?
This project has corruption written all over it. Who are the financiers and in what amounts?
“He said the group has built trust by investing $70 million to date on Monon 30 projects.” WHAT? Who has invested $70 million? What group? And where did the money go?
Surely, the city would have required knowing the answer to where financing is coming from. Otherwise, how do you get $15m of bonding proceeds. So, what is the answer?
Blaming delays on the Metropolitan Development Commission?? Seriously?
And the Domiono “began leasing at the beginning of the year” … 9 months ago. Yet missing from your reporting is what % of units have been leased. (And I would want to see evidence of any claim.) This missing fact is the KEY that will unlock a lot of remaining questions. And at what lease rates compared to other options? And are rents actually being paid?
Did you tour the building? Where are the photos?
How did this project get approvals? Who is behind it?
Johnie Alex? What’s her connection? Why quote her? “retired IBM executive”?? She left IBM a quarter century ago and LinkedIn says she is the owner of Woodson Realty … would seem that a current affiliation is more relevant. What’s going on here?
“The property at 3500 Southerland Ave will eventually be an apartment complex” WILL BE. Really? You meant is planned to be. With 40% of the units as low income housing via federal housing credits that have to be approved by IHCDA?? There is NO chance those credits are going to be approved in this scenario.
This project is an obvious absolute disaster. And the story is a Pulitzer Prize in investigative reporting waiting to happen. What is the hold-up?